greatlakesCook SWCD was awarded a Great Lakes Commission grant in 2010 to complete various projects on Caspers Hill Road to reduce erosion impacting the Little Brule River and Gauthier Creek, both designated trout streams.

Upon completion of field work and sediment reduction project designs (completed by Cook SWCD and TSA3 staff) construction commenced and was completed in September 2011. Caspers Hill Road is a private road and Cook SWCD received support and a portion of the match (funding) for this project from the landowners.

Sediment reduction projects completed at Caspers Hill Road site included:
• Erosion control around Little Brule Creek
• Two culvert replacements
• Ditch stabilization
• General road erosion control including road crowning, road tilting, and water bars.

Before and after photos of a few of the projects are shown below in Figures 1 to 8. Cook SWCD would like to thank the Great Lakes Commission and the landowners on Caspers Hill Road for their support.

site1

site2

Figure 1. Site 1- November 2010 Figure 2. Site 1 - September 2011

site3

rocks

Figure 3. Site 2 - November 2010 Figure 4. Site 2 - September 2011

site9

site4

Figure 5. Site 3 - May 2011 Figure 6. Site - 3 September 2011

site5

site6

Figure 7. Site 4 November 2010 Figure 8. Site 4 - September 2011

 

Soil and Water - Upcoming Events

View Full Calendar

Soil & Water

District Manager
Kerrie Fabius
(218)387-3649
Water Plan Coordinator
Ilena Berg
(218)387-3648
Program Assistant
Theresa Oberg
(218)387-3647

LOCATION
Cook County Courthouse
411 W. 2nd Street
Grand Marais, MN  55604

HOURS
8AM-4PM  M-F

PHONE
(218)387-3647

EMAIL
soilandwater@co.cook.mn.us

 

Feedback Form
Customer Feedback