Precast Concrete $ 1 25,000.00 Rebid phase $ 125,000.00 Aluminum Doors and Windows $ 75,000.00 Redesign/VE $ 75,000.00 HVAC $ 2 00,000.00 Awaiting Eng. Approval $ 200,000.00
Electrical $ 25,000.00 Awaiting Eng. Approval $ 18,372.00 Masonry $ 20,000.00 Arch. approved $ 20,000.00 Concrete $ 100,000.00 Arch. approved $ 92,252.00 Exterior Improvements $ 239,071.00 Arch. approved $ 216,506.00 Athletic Equipment $ 40,000.00 Arch. approved $ 61,799.00 Utilites $ ‐ Awaiting Eng. Approval $ ‐ Earthwork $ 5 52,100.00 Arch. approved $ 552,100.00 Pool Aquatics $ 100,000.00 Arch. approved $ 76,000.00 Roof $ 75,000.00 Arch. approved $ 65,000.00 Flooring $ 10,000.00 Awaiting Arch. Approval $ 10,000.00 Plumbing $ 50,000.00 Awaiting Eng. Approval $ 7,000.00 Metal $ ‐ Awaiting Arch. Approval $ 6,215.00 Reduce Building Footprint $ 400,000.00 Arch. approved $ 400,000.00 FF & E $ 300,000.00 YMCA Approved $ 300,000.00 Demolition Grant $ 103,000.00 State Approved Grant $ 103,000.00 TOTAL VE SAVINGS $ 2,414,171.00 $ 2,328,244.00 LOCKBOX ($500,000) $ (500,000.00) CURRENT $ 1,828,244.00 ORIGINAL AMOUNT NEEDED $ 1,966,024.00 SHORTAGE TO BE MADE UP $ (137,780.00) Precast Define panel color 8' wide panels 12" thick panel No recess in the exterior $ 125,000.00 Rebid Total Savings $ 125,000.00 Aluminum Doors and Windows Change curtain wall detail to storefront detail Change in design Alternate door frames Typical VE item 7' tall doors in place of 8' Typical VE item Reduce window sizes at pool Eliminate scope Delete transom and sidelights at back entrance Eliminate scope Delete requirement for structural engineering Eliminate scope $ 75,000.00 Total Savings $ 75,000.00 HVAC Simplify Johnson Controls Eliminate scope Gas fired rooftop units in place of hot water coil roof top units Typical VE item Alternate duct layout for gym area Typical VE item One larger roof top unit in place of two smaller ones Eliminate scope $ 200,000.00 Total Savings $ 200,000.00 Electrical Alternate fixture package Typical VE item Type Qty Description Unit deduct Ext. A1, A1E, 20 Standard A12125 lens, flush steel door, eliminate PAF $8.00 $160.00 A5, A5E, A6, A6E 32 Steel housings with Aluminum door frames. $20.00 $640.00 A1E, A4E, A5E, A6E, C1E, C2E, F1E, H1E, 39 Delete self‐diagnostic feature in EL batteries $30.00 $1,170.00 A3, A3E, A4, A4E, A4/MS, 78 Change to Lithonia 2VT series volumetric. $8.00 $624.00 D1, D1E, 49 Change to Lithonia fluorescent $75.00 $3,675.00 D11, D11E 3 Change to MH $75.00 $225.00 E1, E2 9 Change to EDG series edge lit exit $60.00 $540.00 F1, F1E 36 Change to EJS series Lithonia $8.00 $288.00 R3, R3E 4 Change to MH $75.00 $300.00 S1/S1E 1 Lot change tp Peerless 10CRM4 series $750.00 $750.00 Controls 1 Eliminate BacnetIP interface $1,600.00 $1,600.00 Site AA1, AA2, AA# 16 Change site to Lithonia KAD MH $525.00 $8,400.00 288 Total Savings $18,372.00 Masonry Delete brickwork on front $ 20,000.00 Eliminate scope Total Savings $ 20,000.00 Concrete Item Description Savings Eliminate Post‐Tension Concrete at Tennis Courts $ 72,841.00 Eliminate scope Eliminate Sidewalk, Curb, Stairs at Tennis Courts $ 11,770.00 Eliminate scope Eliminate Curb and Gutter at North Parking Lot $ 7 ,641.00 Eliminate scope Total Savings $ 92,252.00 Exterior Improvements Item Description Savings Delete paving at softball field Alternate spec mix for asphalt $ 45,000.00 Eliminate scope Delete softball fencing $ 62,746.00 Eliminate scope Delete retaining wall fencing $ 10,325.00 Eliminate scope Delete retaining walls $ 50,000.00 Eliminate scope Delete paving at north parking strip Eliminate scope Eliminate tennis court fencing $ 37,365.00 Eliminate scope Eliminate tennis court surfacing $ 11,070.00 Eliminate scope Total Savings $ 216,506.00 Athletic Equipment Eliminate dug outs, bases, benches, fence toppers and foul posts $ 30,314.00 Eliminate scope Eliminate Tennis posts, nets and wind screens $ 12,130.00 Eliminate scope Do not replace existing basketball backboards and goals $ 19,355.00 Eliminate scope Total Savings $ 61,799.00 UTILITES Eliminate lift station for draining ground water at pool Eliminate scope Total Savings $ ‐ Earthwork Delete work at soccer field $ 94,800.00 Eliminate scope Delete all work at ball field $ 457,300.00 Eliminate scope Total Savings $ 552,100.00 Pool Aquatics Eliminate 1 bench $ 3,000.00 Eliminate scope Reduce depth to 9'‐6" $ 73,000.00 Eliminate scope Total Savings $ 76,000.00 Roofing Alternate insulation type (same rvalue), ballasted/adhered combination in place of all adhered roof $ 65,000.00 Change in design/typical VE item Total Savings $ 65,000.00 Flooring Verify floor finishes in offices Eliminate scope Alternate tile Typical VE item Alternate carpet Typical VE item $ 10,000.00 Total Savings $ 10,000.00 Plumbing Alternate fixture package $ 7,000.00 Typical VE item Total Savings $ 7,000.00 Alternate Metal Panels Exposed fastener panel $ 6,215.00 Typical VE item Total Savings $ 6,215.00 Reduce Building Footprint Reduce square footage of building by 3,400 sf by making lobby/entrance area smaller. The dollar amount assumes a savings of $118.00/square foot over an area of 3,400 square feet. The savings would come from a reduction of scope in all bid packages. $ 400,000.00 Eliminate scope Total Savings $ 400,000.00 FF & E Reduce FF & E budget to $300,000 in place of $600,000 $ 300,000.00 Total Savings $ 300,000.00 Demolition Grant $ 103,000.00 Total Savings $ 103,000.00
|